Projects
Platte West
Owner: Metropolitan Utilities District
General Contractor: Alberici Constructors, Inc
Architect/engineer: HDR
Value: $7,794,116.00
Judds Bros Construction Co provided all supervision, labor, material, tools, and
equipment to complete all yard piping from 1 inch through 72 inches including civil
site, drainage, chemical injection vault and appurtenances. The project also
included manholes, inlets, junction boxes, drain boxes, flared inlet sections, pond
inlets, and outlets and chemical duct banks. There are 92,000 LF of pipe involved.
Lincoln B2 West Fueling Facility
Owner Burlington Northern Railroad Company
Architect/Engineer APA, Inc.
Value $6,050,000
Lincoln B2 West Fueling Facility involved construction of a new fueling facility
on the south side of Hobson Yard, near its western end. Work included a diesel fuel
oil loading/unloading facility, fueling platform, underground utilities and structures.
We also constructed a new diesel fuel oil tank at the Cushman site west of 40th
Street.
Minuteman II Dismantlement, Whiteman Air Force Base, Missouri
Owner Department of the Army, Omaha District,
Corps of Engineers
Architect/Engineer U.S. Army Engineer District,
Corps of Engineers, Omaha, Nebraska
Value $6,500,000
As a sub-contractor to M.A. Mortenson Company, Judds Bros. Construction Co. completed
all appurtenant work to dismantle150 Minuteman Intercontential Ballistic Missile
(ICBM) Launch Facilities using mechanical demolition methods to remove and dispose
of the topside appurtenances and all below grade construction to the required elevations.
Lincoln Water System, Modifications to Water Pumping Stations
Owner City of Lincoln, Nebraska
Architect/Engineer Olsson Associates & Black
& Veatch
Value $3,995,000
Judds Bros. Construction Co. is furnishing and installing piping, pumps, pump motors,
flow tubes, butterfly valves, electrical transformers, switchgear, instrumentation
and control equipment, and all other appurtenant work to "A" Street, Belmont,
Merrill, Southeast and 51st Street Pumping Stations.
48" Water Main in McKinley WC7746
Owner Metropolitan Utilities District
Architect/Engineer Metropolitan Utilities District
Value $2,055,000
We Installed approximately 9,300 LF of 48" Ductile Iron Water Main and relocated
approximately 950 LF of 8" Ductile Iron Water Main from 48th and McKinley Street
to 63rd and Rainwood Road
Solids Handling and Processing Improvements, Northeast Wastewater Treatment Facility
Owner Lincoln Wastewater System
Architect/Engineer HDR Engineering, Inc.
Value $4,055,000
Construction of two (2) 2,000 gpm production wells with masonry well houses and
approximately 1,100 LF of 16-inch diameter transmission main.
Kerford Limestone - New Mine Entrance
Owner Kerford Limestone Company
Architect/Engineer Chuck Soukup
Value $750,000.00
Install foundations, conveyors, transfer points, crushing equipment and associated
equipment in the construction of a new underground limestone mine.
Millwright Customers
Judds Bros. Construction Co. has also established themselves doing time and material
work for local Companies in and around the Lincoln, Nebraska area. We have cultivated
relationships with the following customers:
Kerford Limestone: Frank Cranston
Purina Mills: Kent Zimmerman
Crete Mills (Lauhoff Grain): Steve Slaven
Deeter Foundry: Jeff Tomhave
Nebraska Ash Company: Tex Leber
Sanitary Sewer - Phase 2, Collection and Treatment System, (Betty, Chris & Hanson Lakes)
Owner Sanitary and Improvement District No. 101
of Sarpy County, Nebraska
Architect/Engineer Olmsted & Perry Consulting
Engineer, Inc.
Value $4,200,000.00
Treatment System - Judds Bros. Construction Co. built an on-site constructed wetlands
wastewater treatment system, consisting of site grading, splitter structure, pretreatment
tanks, filter tanks, subsurface constructed wetlands system, dosing tank, pumps,
piping, flow meter, UV disinfection system, control building and related appurtenances.
Railroad Transportation Safety District, Railroad Track Consolidation Project
Owner City of Lincoln, Nebraska
Value $3,950,000.00
The work of this project consisted of the construction of railroad trackbed and
tracks, including bridge structures and miscellaneous related work for the consolidation
of railroad services in Lincoln, Nebraska. The rail work of this project included
the following activities:
The complete construction of new tracks, including subgrade for new tracks for the
Omaha, Lincoln & Beatrice Railway.
The reconstruction of roadway approaches to the BNSF railroad grade crossings on
14th and 17th Streets, the construction of new subgrade for new railroad crossings
of those roads and the placement of temporary pavement in the future track area.
The removal of abandoned Union Pacific Railroad tracks and other facilities in the
"X" Street corridor between the BNSF, in the vicinity of 10th Street and
approximately 19th Street, including the reconstruction and restoration of intersecting
streets and sidewalks, the clearing and seeding and mulching of the railroad right-of-way
and miscellaneous work.
Lancaster Event Center
Owner Lancaster County Agricultural Society,
Inc.
Architect/Engineer Design Associates
Value $6,550,000.00
Judds Bros. Construction Co. coordinated and performed work to complete the construction
of a public, multipurpose year round facility designed to host a variety of local,
regional and national events and activities. The center features three interconnected
structures that include the multi-purpose arena, and two multi-purpose pavilion
adjacent to an outdoor arena. The multi-purpose arena is a rectangular 65,500 SF
area. Pavilion I and Pavilion II are 80,000 SF each.
Lincoln Water System, Expansion of Water Supply, Treatment and Transmission Facilities, Northeast Pumping Station and Reservoir Modifications
Owner City of Lincoln, Nebraska
Architect/Engineer Lincoln Water Consortium:
Black & Veatch, HWS Consulting Group, Inc., Olsson Associates, Sinclair Hille
& Associates
Value $5,675,000.00
The contract included construction of a 5.1 million gallon below-grade ground storage
treated water reservoir of cast-in-place concrete construction and associated 48-inch
and 54-inch yard piping adjacent to the existing Northeast Pumping Station and Reservoir.
A single 20.2 mgd low head pumping unit was installed and wetwell modifications
provided in the existing Northeast Pumping Station, along with modifications of
the facilities electrical and heating, ventilation, and air conditioning systems.
Lincoln Water System, Expansion of Water Supply, Treatment and Transmission Facilities, Vine Street Pumping Station and Reservoir
Owner City of Lincoln, Nebraska
Architect/Engineer Lincoln Water Consortium:
Black & Veatch, HWS Consulting Group, Inc., Olsson Associates, Sinclair Hille
& Associates
Value $7,800,000.00
The contract included construction of a 10 million gallon below-ground storage treated
water reservoir of cast-in-place concrete construction with a High Service Pumping
Station integrally constructed within the new reservoir. The reservoir and pumping
station were constructed adjacent to the existing 10 million gallon Vine Street
Reservoir. Two 10 mgd vertical diffusion vane pumping units were furnished and installed
in the pumping station. The contract also included construction of a reservoir overflow
structure, flow control vault, meter manhole, retaining walls, major yard piping
ranging from 54-inch to 20-inch diameter, piping and electrical modifications at
the existing Vine Street Pumping Station and associated electrical work, control
and instrumentation work, mechanical work, site work, and all other appurtenant
work.
Carlos Street Water Improvement
Owner City of Lincoln Water System
Architect/Engineer Kirkham, Michael, Schemmer and Associates
Value $ 3,500,000.00
The project included the furnish and install of 5,600 LF of 54 inch steel water
main. Also relocation of 8 inch sanitary sewer on Carlos Drive and various
storm sewer extensions. The below ground improvements also includes the removal
and repaving of Carlos Drive from East Avon Lane to Holdredge Street.
ADM Dry Mill Underground
Owner Archer Daniels Midlands
Architect/Engineer N/A
Value $672,280.00
The project included installation of 10,000 LF of 16-inch ductile iron fire main
and all appurtenant work. Also installed 3,300 LF of carbon steel chilled
water supply and return line ranging in size from 30-inch thru 78 inch. There
is also installation of 5,280 LF of 8 inch sanitary sewer and associated manholes.
All piping was below ground. Owner furnished all pipe and appurtances.
City Mission Addition, Lincoln, NE
Owner: Curtis Center Housing, L.P.
Architect/Engineer Design Associates of Lincoln,
Inc
Value $ 2,500,000.00
Judds Brothers Construction Co. coordinated and performed work to complete
the construction of a single level, multi-purpose facility designed as a male housing
unit. There is 18,000 SF of space including two interior court yards and a
new dining room incorporated into this project. The wood framed addition has a masonry
exterior and is complete with mechanical and electrical work. This is a year
around addition with a sprinkler system.
Council Bluffs Energy Center Rail Expansion
Architect/Engineer: Burns & McDonnell
Value of Project: $1.48 million
The construction for this project included a new rail overpass consisting of installing
a 31 ft. diameter culver to allow for train traffic to go under the new access road
over the track. The project included the grading for the overpass, relocation
of existing waterlines, the laying of the culvert pipe allowing the track to go
underneath the new overpass, laying of new track going through the culvert, storm
drainage, paving of the new road on the overpass, signage and street lighting.
Northeast Community Recreational and Sports Complex
Owner Joint Antelope
Valley Authority (JAVA)
Architect/Engineer Parsons Brinckerhoff, Olsson
Associates, Sinclair Hille Associates
Value $3,279,000
The project includes construction of four (4) ball fields, multi-purpose field, multi-purpose courts, concession building, picnic shelter, parking lot, removal and installation of railroad track, loadout building and associated work for completion of the project.
Brownell Elementary School and Multi-purpose Room and Indoor Air Quality Project
Owner Lincoln Public Schools
Architect/Engineer Architectural Design Associates,
P.C.
Value $3,517,000
Addition of a Multi-purpose Room and renovations associated with a new heat pump
system.
Lincoln East High School Classroom Addition
Owner Lincoln Public Schools
Architect/Engineer Sinclair Hille and Associates,
Inc.
Value $4,000,000
Judds Bros. Construction Co. performed the work to complete this project, which
involved the new construction of general-purpose classrooms, science classrooms/labs,
ancillary science rooms, teacher work areas and the enclosing of an existing exterior
courtyard for use as a multi-purpose room. The remodeling portion of the contract
included remodeling the existing science classroom/labs, teacher work areas and
sprinkler system. There was approximately 36,000 SF of new construction and 14,000
SF of remodeled space incorporated into this project. Judds Bros. Construction Co.
completed the steel erection with our own forces and also various miscellaneous
appurtenant tasks.
I-80 Scales and Scale Buildings
Owner The Nebraska Department of Road s
Architect/Engineer Davis Design
Value $2,800,000
Largest scale site in the State of Nebraska, consisting of four buildings, two operation
stations and two truck inspection facilities. The Nebraska State Patrol Carrier
Enforcement Division for certifying legal weight limits of commercial vehicles and
inspection of the same operates this facility. This was a highly technical project
featuring Nebraska's only weigh station to have both directions of traffic equipped
with a Weight In Motion (WIM) scale system. This project involved a short time frame
with coordination between Judds Bros. Construction Co., the paving contractor and
the owner, which made this a truly unique project.
Judds Bros. Construction Co. completed all structural work on this project including
the foundations, wood framing, pre-engineered buildings, floor slabs, inspection
pits, and the WIM vaults incorporated into interstate I-80.
The construction included a unique round design for high visibility of interstate
traffic, and incoming and outgoing vehicles. The conical roof framing with its complex
design required highly skilled carpenters. There are also truck inspection pits
for easy access to the underside of vehicles. The Static Scales are designed and
built for years of service at an estimated 24,000,000 trucks per year. The Weight
In Motions Scales are employed as a sorting device to aid in the selection of trucks
to be brought into the station for weighing.
Dawes Middle School Indoor Air Quality Improvements
Owner Lincoln Public Schools
Architect/Engineer Architectural Design Associates, P.C.
Value $4,424,000
Renovation of existing facility which included new heating, cooling, and electrical
systems, a geothermal well field, and penthouses. Construction of new roofing
system and fire protection system for existing structure.
Faith Lutheran Church, Phase I & II
Owner Faith Lutheran Church
Architect/Engineer JEO Consulting Group, Inc.
Value Phase I - $2,800,000, Phase II - $2,400,000
The project consists of the construction of an approximate 30,000 square foot, two
story, steel framed, composite slab, steel stud/masonry/EFIS exterior, steel stud
interior partitions, complete with all mechanical and electrical work.




















